Two Norochcholai units to rejoin national grid today
Photo: Daily MirrorAI summary · 1 min read
1 min readFrom 7 outlets- The grid disruption left all three Norochcholai units out of service, according to Ada Derana (தமிழ்).
- The National System Operator said Unit 3 was reconnected early on October 23, with Unit 1 planned for later that day, Newsfirst (සිංහල) reports.
- Reports later said all three units were operating or reconnected.
- The Energy Ministry said restarting the plant requires inspections and a gradual return to operating conditions, Daily Mirror reports.
Your take
Be the first to reactDiscussion
Readers' views on this storyStory alerts
Get an email when an outlet reports something new on this story.
Compare the headlines
The same event, in each outlet’s own words. The order changes daily.
Daily MirrorEN
Why does it take days to restart Norochcholai power plant?Hiru News (සිංහල)SI
නොරොච්චෝලේ තුන්වන ජනන යන්ත්රයත් පද්ධතියට එක්කරයිAda Derana (தமிழ்)TA
நுரைச்சோலையின் மூன்று மின் பிறப்பாக்கிகளும் மீண்டும் இயங்குகின்றனRupavahini NewsSI
නොරොච්චෝලේ අද සිට යළි ජාතික පද්ධතියට
Earlier coverage
Reports on the same subject from the months before this story.
- Hiru News (සිංහල) · නොරොච්චෝලේ බලාගාරයේ විදුලි ජනන ඒකක තුනම අක්රිය වෙයි
- Daily Mirror · Norochcholai power plant to remain offline for several days
- Lankadeepa · සෙනසුරාදා රටම අඳුරුවුණේ නොරෙච්චෝලේ අවුලකින්
- Hiru News (සිංහල) · අක්රීය වූ නොරොච්චෝලේ තාප බලාගාරයේ එක් ජනන යන්ත්රයක් හෙට පද්ධතියට එක්වන ලකුණු
- Hiru News (සිංහල) · ලක්විජය දෙවන ඒකකය යළි ක්රියාත්මක කිරීමත් සමග අද සිට විදුලි ඉල්ලුම කළමනාකරණය කිරීමේ පියවර තවදුරටත් අවශ්ය නොවේ - ජාතික පද්ධති ක්රියාකරු (පුද්ගලික) සමාගම